Week of June 1, 2026
The only really new thing is the construction of the ADA pedestrian ramp. Still many many dump truck loads of dirt (layered with mesh and contained on the sides by the black fabric) continue to roll in reverse along Olympiad. The "stair steps" will be filled to create the ramp.
The photo on the left shows the non-ramp side of the approach to the bridge deck. The walls we see in the photos will be covered with a concrete fascia.
Week of June 8, 2026
Dump trucks continue to bring in dirt!
On Tuesday, long, side-dump trucks removed some of the tree trunks and roots left from clearing the bank above the east end of the bridge.